Panama Canal: A Mega Container Lane

Twitter
Facebook
LinkedIn
Email

A video released by the Panama Canal Authority shows the January, 2016 update of the ongoing expansion project, which is due to open in the second half of 2016.

The overall expansion project is now 96% complete, with the third set of locks currently at 95% completion. The construction of 32 buildings continues, after 4.4 milllion cubic metres of structural concrete was removed.

The flooding of a new channel began in September, 2015, and will contain approximately 19 cubic metres of water. The 13-kilometre culera cut has also been cut to meet the needs of larger ships.

(Source: Panama Canal / YouTube)

Daily Email Newsletter

Sign up to our daily email newsletter to receive the latest news from Port Technology International.
FREE

Supplier Directory

Find out how to get listed

Webinar Series

Find out how to attend

Latest Stories

Cookie Policy. This website uses cookies to ensure you get the best experience on our website.