New terminal at Walvis Bay becomes fully operational

Twitter
Facebook
LinkedIn
Email
a1-walvis_namibia_wbcp

The new container terminal at the Namibian Port of Walvis Bay is now fully operational, according to a report by the African Development Bank (ADB).

In a statement, the ADB said the terminal was built on constructed on 40 hectares of land reclaimed from the ocean by China Harbor Engineering Company Ltd (CHEC) as part of a project worth $300 million.

It will, according the the bank, turn Walvis Bay into becoming a logistics hub for southern Africa to meet the growing regional demand for freight and provide maritime access for landlocked countries of the Southern Africa Development Community (SADC).

The African Development Bank provided a ZAR 2,982 million ($178 million) loan representing over 70% of the project funding.

The works included the dredging over 3.9 million cubic metres of sand, used partly for the reclamation, construction of a 600-metre quay wall, the laying of 304,000 square metres of paved surface and the construction of a workshop and administrative buildings.

It also entailed the installation of four ship-to-shore (STS) cranes, the construction of a one-kilometre road, the laying of 2.3 km of rail lines, and the installation of service networks. The facility’s electricity supply was also successfully upgraded, the report noted.

“Overall, the project has fully achieved its goals,” the report said, increasing the terminal’s capacity from 355,000 TEUs (20-foot equivalent unit) to 750,000 TEUs yearly. It has also reduced vessel waiting time to less than 8 hours and cut container transit time from 14.5 days to 9.5 days. 

Expanded activities required the training of seven pilots and 26 ship-to-shore crane operators, including one woman.

The demand for services from the port of Walvis Bay has increased by about 8% following the commissioning of the new terminal, the report notes. Cargo volumes, revenues and income from other services (maritime, port, berth and light dues, and other storage and handling fees) are expected to increase by at least 8% in 2020 and 2021. After that, growth should reach 5% yearly the report projects.

The project completion reporting team was led by Richard Malinga, Bank Principal Transport Engineer and Task Manager for the project.

The Walvis Bay expansion aligns with the Bank’s High-5 strategic priorities, including promoting the integration of Africa.

Daily Email Newsletter

Sign up to our daily email newsletter to receive the latest news from Port Technology International.
FREE

Supplier Directory

Be listed with industry leaders operating within Ports and Terminals

Webinar Series

Join 500+ attendees on average with a Port Technology International webinar

Latest Stories

Cookie Policy. This website uses cookies to ensure you get the best experience on our website.